Lamido Aliyu Mustapha Flyover, Yola

Country
Nigeria
Sector
Transport
Intelligence Type
Project
Status / Stage
Completed
Estimated Value
NGN ₦3,043,853,469.56
Confidence
Confirmed

Project Details

Project TypeFlyover
Project OwnerAdamawa State Government
Project SponsorAdamawa State Government
Main ContractorTriacta Nigeria Limited
Project DeveloperAdamawa State Government
Start Date5 August 2020
Expected Completion2021
Actual Completion29 May 2021
Current PhaseOperational
Funding StatusClosed

Key Issues / Risks

No major unresolved construction issue identified from the sources reviewed. The project is currently treated as completed and operational.

What Happens Next

Continue monitoring the operational condition of the flyover, subsequent maintenance or modification contracts, traffic-management interventions and any additional works connected to the structure.

Commercial Opportunity

Historical construction opportunity: Closed.

Current opportunity: Maintenance, road-safety infrastructure, signage, drainage, traffic management and related urban infrastructure contracts may arise around the asset, subject to future procurement.

Capital & Financing Intelligence

Funding / Amount Committed₦3,043,853,469.56
Funding SourceAdamawa State Government
Funding Date2020

Commercial Opportunity Intelligence

Commercial ReadinessAwarded

Historical Intelligence

5 August 2020 — Project Flag-Off
Governor Ahmadu Umaru Fintiri formally flagged off construction of the Lamido Aliyu Mustapha Flyover at the Total Filling Station Junction, Jimeta. The contract was awarded to Triacta Nigeria Limited at ₦3.043 billion.
August 2020 — Construction Begins
Physical construction commenced following the formal project flag-off.
2020–2021 — Construction Phase
Triacta Nigeria Limited executed the flyover and associated road infrastructure.
29 May 2021 — Completion & Commissioning
The completed flyover was commissioned as part of the 2021 Democracy Day activities, marking the project's transition from construction to operational public infrastructure.
Current — Operational
The flyover is classified as Completed / Operational and remains part of Adamawa State's urban transport infrastructure.

Analyst Notes

Important verification note: The ₦3,043,853,469.56 figure relates specifically to the Lamido Aliyu Mustapha Flyover; it should not be combined with the ₦5,089,580,087.69 cost of the separate Police Roundabout Grade Interchange.

The Lamido Aliyu Mustapha Flyover was developed at the Total Filling Station Junction in Jimeta, Yola, as part of the Fintiri administration's urban renewal programme. The project was intended to improve traffic flow at a major intersection and reduce congestion associated with increasing urban traffic.

The project included the flyover structure, a ground-level roundabout for traffic distribution and additional lanes along the adjoining roads. The contract was awarded to Triacta Nigeria Limited.

At ₦3.043 billion, it was one of the two major grade-separated transport projects flagged off by the Fintiri administration in August 2020. The other, the Police Roundabout Grade Interchange, was separately valued at approximately ₦5.09 billion.

The flyover was completed and commissioned on 29 May 2021, with former Vice President Atiku Abubakar performing the commissioning.