NLNG Train 7 (Bonny Island LNG Expansion)

Country
Nigeria
Sector
Oil & Gas
Intelligence Type
Project
Status / Stage
Pre-Commissioning
Estimated Value
USD 5000000000
Confidence
Highly Confirmed

Project Details

Project TypeLNG Processing Train
Project OwnerNigeria LNG Limited (NNPC, Shell, TotalEnergies, Eni)
Main ContractorSCD JV Consortium (Saipem, Chiyoda, Daewoo E&C)
Financing InstitutionNLNG shareholders
Start DateJuly 2018 (FEED); FID December 2019; EPC awarded May 2020
Expected CompletionCommissioning 2027
Current PhaseCommissioning
Funding StatusClosed

Key Issues / Risks

Multi-year delay from COVID-19 pandemic and 2022 Russia-Ukraine conflict supply chain disruption.

Latest Development (Detail)

92% complete as of May 2026, now advancing into systems completion and pre-commissioning. Commissioning is scheduled for 2027. When operational, production capacity increases from 22 MTPA to 30 MTPA.

Commercial Opportunity Intelligence

Commercial ReadinessVery Early

Source & Verification Trail

Last VerifiedMay 2026
Source(s)NLNG official project page; Global Energy Monitor; Saipem project page
Source DateMay 2026

This project has been fully tracked to completion. Read the complete Project Dossier →