Project Risk Allocation: The Risk Matrix Lenders Read

Every project can go wrong in many ways. A well-structured project assigns each risk to the party best able to manage it, and lenders review a risk matrix to check that no major risk is left without an owner.

The golden rule

Give each risk to the party that can control it, or insure against it, at the lowest cost. A contractor can manage construction methods, but it cannot control government policy.

Main risks and who usually carries them

  • Construction and completion risk. The project is late or costs more. Usually passed to the contractor through a fixed-price, fixed-date contract, backed by damages and guarantees. Sponsors may support during construction.
  • Performance risk. The plant does not work as promised. Contractor and equipment suppliers, through performance tests and warranties.
  • Market or offtake risk. Nobody buys the output, or the price falls. Passed to a creditworthy buyer through a long-term sales contract, such as a power purchase agreement.
  • Supply risk. Fuel or raw materials are unavailable or too expensive. Passed to suppliers under long-term supply contracts, or to the buyer.
  • Operating risk. Running costs rise or the plant breaks down. Operator, through an operation and maintenance contract.
  • Currency and interest rate risk. Costs or income move against the loan. Managed through hedging, matching currencies, or indexation.
  • Political and regulatory risk. Governments change the rules, delay permits or interfere. Managed through government support agreements, political risk insurance and development finance institutions.
  • Environmental and social risk. Community opposition or environmental damage. Managed through impact studies, consultation and compliance with recognised standards.
  • Force majeure. Events nobody controls. Dealt with through insurance and contract relief.

What lenders do with the matrix

They check that each risk has a clear owner, that the owner is strong enough to cover it, and that contracts back the arrangement. Any gap means more equity, more security, or a different structure.

Key takeaways

  • Risk goes to the party best able to manage it.
  • Lenders check that every major risk has a strong owner.
  • Contracts, insurance and guarantees make the allocation real.
  • Gaps lead to higher cost or no funding.