When an official says a country has thousands of megawatts, ask which number they mean. The gap between paper capacity and delivered power is where most power-sector problems live.
The idea in plain English
Installed capacity is the plant’s nameplate rating. Available capacity is what can actually run on a given day after maintenance, fuel shortages and low water levels. Dispatched power is what actually flows into the grid, based on demand and what the network can carry.
How it works in practice
Plants lose availability through maintenance, gas shortages, low river levels and equipment faults. Even available plants may be unable to dispatch if transmission lines are constrained or the grid operator limits output to keep the system stable. Delivered energy also depends on customers’ ability to pay.
What to do with this
- Ask for availability and dispatch history, not only nameplate capacity, when assessing a power asset.
- Check whether the plant’s output is limited by fuel supply, transmission capacity or payment delays.
- Negotiate deemed energy or capacity payment terms so you are paid when the plant is available but cannot dispatch.
Where it goes wrong
Revenue models built on installed capacity at high load factors overstate returns. Use realistic dispatch assumptions based on the grid’s actual record.