Pre-Commissioning and Commissioning: Why “Mechanically Complete” Does Not Mean Gas Is Flowing

The most misunderstood milestone in a pipeline project is the gap between finishing the pipe and delivering the gas.

The idea in plain English

Before gas flows, a pipeline is tested with water at a pressure above its operating pressure, known as a hydrotest, then dewatered, dried and purged. Commissioning then brings stations, valves and control systems online, and first gas is introduced step by step.

How it works in practice

Pre-commissioning includes cleaning, gauging, hydrotesting and drying. Commissioning then energises stations, instrumentation and safety systems, and introduces gas in stages while operators confirm that everything holds. Handover involves documentation, operator training and agreed performance tests.

Why it matters: This phase is where schedule slippage is common, and where late-stage suppliers and service companies are brought in.

What to do with this

  1. Ask for the commissioning plan, including who carries out each step and what approvals are needed.
  2. Position testing, instrumentation, control and training services for this stage, since they are often contracted late.
  3. Do not set your own production start against mechanical completion. Wait for confirmed first gas at your connection point.

Where it goes wrong

Sponsors announce near-complete status while connections, stations or approvals remain. Customers who plan to switch fuel on that basis can face months of double running costs.