Liquidated Damages: The Price of Finishing Late

Imagine a toll road that was meant to open in March. Each day it stays closed, the owner loses toll income and may owe money to lenders. Proving the exact loss in court would be slow and expensive. So the contract fixes an amount in advance. These are liquidated damages.

What they are

Liquidated damages, often written as LDs, are a pre-agreed amount of money that the contractor pays the owner for each day, or week, of delay. The amount is set in the contract before work starts and is meant to be a fair estimate of the owner’s loss.

Why they exist

  • They give the contractor a clear reason to finish on time.
  • The owner does not have to prove its actual loss.
  • Both sides know the maximum exposure from the start.

Two common types

  • Delay damages: paid for each day after the agreed completion date.
  • Performance damages: paid if the finished plant does not meet agreed performance targets, such as output or efficiency. These are common on power plants and factories.

The cap

Most contracts cap liquidated damages at a percentage of the contract price. The level varies by contract and sector, and ten per cent is a figure often seen in practice. Lenders look closely at the cap, because it limits how much the owner can recover if the contractor is badly late.

The important rule

Liquidated damages are meant to be a genuine estimate of loss, not a punishment. In some legal systems, a clause that works as a penalty may be unenforceable. The rules differ between countries, so legal advice matters when drafting.

Liquidated damages only run when the contractor is late by its own fault. If the contractor is granted an extension of time, the completion date moves and damages run from the new date. That is why extension claims are so closely fought.

Key takeaways

  • LDs are a fixed, pre-agreed payment for lateness or poor performance.
  • They are usually capped as a percentage of the contract price.
  • They must be a fair estimate of loss, not a penalty.
  • A granted extension of time moves the date from which LDs apply.