Extension of Time and Delay Claims: Who Pays When a Project Runs Late

Few projects finish exactly on the date in the contract. When a delay happens, two questions follow. Does the contractor get more time? And does anyone owe money for the delay? Contracts answer these with extensions of time and delay claims.

Extension of time

An extension of time is more time to complete the work, without penalty. A contractor can usually claim one if the delay was caused by something the contract treats as the owner’s responsibility or as neutral. Common examples are late access to site, late drawings, owner-ordered variations, and some unusual events outside anyone’s control.

If the contractor gets an extension, the completion date moves, and the contractor is not charged for lateness during that period.

Delay costs

Sometimes the contractor can also claim the extra money it spent because of the delay, such as site staff and equipment standing idle. Whether it can depends on the cause. Delays caused by the owner often allow time and money. Delays from neutral events, such as unusual weather, may give time but no money.

What a contractor needs to show

  • Notice. Most contracts require written notice within a set number of days after the contractor becomes aware of the event. Missing the deadline can lose the claim entirely.
  • Cause. The event that caused the delay.
  • Effect on the programme. That the event delayed the work that controls the finish date, known as the critical path.
  • Records. Programmes, site records and correspondence that show what happened.

Concurrent delay

Sometimes the owner and the contractor each cause a delay at the same time. This is called concurrent delay, and how it is treated depends on the contract and the governing law. It is a common source of disputes.

What to do in practice

Give notice early, keep an updated programme, record the effect of each event as it happens, and do not wait until the end of the project to raise a claim.

Key takeaways

  • An extension of time moves the completion date and removes the lateness penalty.
  • Time and money are separate: you can get one without the other.
  • Late notice can destroy a valid claim.
  • Keep an up-to-date programme and records.