Variations and Change Orders: How Scope Changes Get Priced

Imagine you are building a warehouse and the owner decides halfway through to make it ten metres longer. That change is not in the original price. The contract needs a way to add it, price it and adjust the programme. That process is called a variation, or a change order.

What a variation is

A variation is a formal change to the work: adding, removing or changing something compared with the contract. Most construction contracts give the owner the right to order variations, and give the contractor the right to be paid fairly for them.

Why they happen

  • The owner changes the design or requirements.
  • The ground conditions turn out different from the investigation.
  • A new law or regulator’s requirement applies.
  • The design contains errors or gaps.

How a variation usually works

  1. Instruction or request. The owner or its representative asks for a change in writing.
  2. Pricing. The contractor prepares a quote or proposal, showing the cost and any effect on time.
  3. Agreement. The parties agree the price and time, or the owner’s representative decides a fair value if they cannot agree.
  4. Record. The change is written into the contract, so everyone’s paperwork matches.

How a variation is priced

Variations are often priced using the contract’s own rates where they apply. If the work is new, the price is based on reasonable cost plus profit, using records of labour, materials and equipment.

Where disputes start

  • Work done on a verbal instruction, with nothing in writing.
  • A contractor who does not give notice that a change affects cost or time within the time the contract allows.
  • Arguments about whether something was already in the original scope.

Good records protect both sides: written instructions, dated photographs, daily site records and a clear log of every change.

Key takeaways

  • A variation is the formal way to change the scope and price.
  • Get every instruction in writing before the work starts.
  • Give notice on time, because many contracts set deadlines for claims.
  • Keep records of cost and time for every change.

Related explainers

This explainer is general information for learning. It is not legal, tax or financial advice. Rely on the actual contract, law or lender documents for any decision.