FIDIC is the French acronym for the International Federation of Consulting Engineers. It publishes standard construction contracts that are used on many roads, power plants and water projects across Africa, especially those funded by development banks. Using a standard form saves time, because both sides, and the lenders, already know how it works.
The three main books
FIDIC’s best-known forms are named by colour. Each one divides design and risk differently.
- The Red Book is for construction where the owner provides the design. The contractor builds what the drawings show. The owner carries the design risk, and the contractor carries the construction risk.
- The Yellow Book is for plant and design-build projects, where the contractor designs part or all of the works. The contractor carries more of the design risk.
- The Silver Book is for EPC and turnkey projects, where the contractor takes responsibility for design, procurement, construction and getting the facility working. The contractor carries the most risk, and the owner gets the most price and schedule certainty.
Two editions
The first editions of these books were published in 1999, and updated editions followed in 2017. The 2017 editions are longer and add more detail on notices, claims and dispute handling, and some clause numbers differ between editions. Anyone quoting a clause must check which edition the contract uses.
Standard conditions and particular conditions
A FIDIC contract has two main layers. The general conditions are the standard text. The particular conditions are the changes that the parties make for their own project. In practice, the particular conditions often decide who carries the risk, so reading only the standard text is never enough.
What the forms set out
Across the books, the standard text deals with payment, variations, time and delay, bonds and insurance, completion and defects, claims and dispute resolution. Most of the other explainers in this category describe these topics.
Choosing the right book
- Owner has a complete design: Red Book.
- Contractor will design part of the works: Yellow Book.
- Owner wants a finished facility at a fixed price and date: Silver Book.
Key takeaways
- FIDIC forms are widely used on financed infrastructure in Africa.
- The colour of the book tells you who carries the design risk.
- Always check the edition, and always read the particular conditions.
- This explainer is general information. Quote and rely on the actual contract text.
Related explainers
- EPC, EPCM and Design-Build: Who Carries the Risk
- Variations and Change Orders: How Scope Changes Get Priced
This explainer is general information for learning. It is not legal, tax or financial advice. Rely on the actual contract, law or lender documents for any decision.