Lump Sum, Cost-Plus and Unit Rate: Three Ways to Pay a Contractor

Before a contractor starts work, the owner and contractor must agree how the contractor will be paid. That choice decides who pays if costs rise. There are three common methods.

Lump sum

A lump sum contract sets one fixed price for a defined scope of work. If the work costs more than expected, the contractor absorbs it. If it costs less, the contractor keeps the saving.

This gives the owner price certainty, which is why lenders like it. It works best when the scope is clear before work starts. If the design is still changing, a lump sum price is hard to fix, and disputes about what was included become common.

Cost-plus

In a cost-plus contract, the owner pays the contractor’s actual costs plus a fee. The fee can be a fixed amount or a percentage of costs. This is also called a cost-reimbursable contract.

It suits projects where the scope is uncertain, such as complex repairs or fast-track work. The owner carries the cost risk, so it needs good controls: agreed rates, open books and the right to audit. Without them, a cost-plus contract has little incentive to save money, which is why many include a target cost or a cap, with shared savings and overruns.

Unit rate

A unit rate contract, also called remeasurement, prices each item of work per unit, such as a price per cubic metre of concrete or per kilometre of road. The contractor is paid for the quantities actually built, measured on site.

It suits civil work, such as roads and earthworks, where the exact quantities are not known until the work is done. The owner carries the quantity risk, and the contractor carries the risk that the rates are wrong.

Mixing the methods

Many projects combine methods. A power plant might use a lump sum for the main equipment and unit rates for earthworks, because the ground conditions are uncertain.

How to choose

  • Clear scope and a fixed design: lump sum.
  • Uncertain scope or urgent work: cost-plus, with controls.
  • Quantities not yet known: unit rate.

Key takeaways

  • Lump sum gives price certainty but needs a clear scope.
  • Cost-plus gives flexibility but needs tight cost controls.
  • Unit rate pays for measured quantities and suits civil work.
  • Lenders usually prefer price certainty.